Maintenance and modernization |
|
||||
|
At the Arsenal – Bastille marina
● Until 1 April 2009
Work on the port equipment
The current works will be finished at the end of March 2001.
These works consist in changing the 840ml pontoons and renewing the associated equipment: electrical networks, water networks, telecommunications cables, etc.
These pontoons will also be equipped with a vacuum sewage system for recovering wastewater.
● Until July 2009
Refurbishing of the Port authority
The Port authority is reorganizing on two levels:
. 1st level: the ground floor reserved exclusively for operations (employee offices, control room and meeting room)
. The Basin level will be reserved for yachtsmen. It will integrate a relaxation and game room.
● Until June 2009
Closure at the level of the 9th lock
Safety works at the level of the 9th lock (closure by gate and grids) will be conducted for Spring 2009.
● Until June 2009
The quay of the Arsenal - Bastille marina is being modernized to receive botels under the best conditions:
- installation of new electric and water distribution terminals
- suction of wastewater.
These boats no longer need to operate on electric power units.
|